Bathroom renovation price: what it consists of
What the labour rates are for tiling, ceilings and doors, how long a bathroom renovation takes, in what order the work is done and why plumbing is priced separately.
- 5,0 paslaugos.lt
- 15+ years of experience
- Price in the contract
- We reply within 1 working day

Published 2026-10-21. Rates from VP statyba estimates, excluding VAT.
BathroomWhy the bathroom is the most expensive room in a flat
A five-square-metre bathroom brings every trade together: stripping the old finishes, plumbing pipework, electrics, waterproofing, tiling, ceilings, doors and fitting the fixtures. That is why a bathroom renovation costs several times more per square metre than a room, and this is where unforeseen work most often turns up: rotten pipes, uneven walls, damp under the old bath.
Labour rates from our estimates
Prices excluding VAT, for labour:
| Labour | Pcs | from, € excl. VAT |
|---|---|---|
| Stripping old finishes and partition walls | m² | 15–20 |
| Wall and floor tiling | m² | 32 |
| Plasterboard ceiling, 2 layers, with framing | m² | 45 |
| Ceiling skimming | m² | 6 |
| Ceiling painting, 2 coats | m² | 9 |
| Self-levelling floor compound | m² | 18 |
| Internal door installation | pcs | 143 |
| Socket / switch | pcs | 10 |
We price plumbing pipework, waterproofing, electrical wiring and fixture installation for each specific bathroom, because it depends on the number of outlets, the length of pipe runs and whether the risers are being replaced. Materials (tiles, taps, shower enclosure) are chosen by you and entered in the estimate as a separate line.
Example: a 5 m² bathroom with toilet, finishing works only
- Stripping old finishes, about 25 m²: 500 €
- Floor levelling, 5 m²: 90 €
- Wall tiles, about 22 m²: 704 €
- Floor tiles, 5 m²: 160 €
- Plasterboard ceiling, filling and painting, 5 m²: 300 €
- Door and 3 sockets: 173 €
Finishing work about 1 927 € excluding VAT. Plumbing, electrics, waterproofing and materials are added on top. An indicative total with materials for your chosen level is shown in 2 minutes by calculator.
Process and timescales
- Dismantling and removal, 1–2 days.
- Plumbing and electrics: new pipes, risers and outlets, 2–3 days.
- Wall and floor levelling, waterproofing, 2–3 days including drying time.
- Tiles for walls and floors, grouting, 4–6 days.
- Ceilings, doors, fixtures, cleaning and handover, 2–3 days.
A full bathroom renovation takes about 2–3 weeks. We write the timeframe into the contract, and you pay in stages for the work already completed.
What most often increases the estimate
- Replacing risers, which needs to be agreed with the neighbours.
- Uneven walls that need plastering before tiling.
- Large-format tiles and complex patterns, which are slower to lay.
- Relocating the bath and shower when the waste pipes are moved.
Related services
Frequently asked questions
Can you renovate just the bathroom without touching the rest of the flat?
Yes, we also carry out bathroom renovation as a standalone job. It usually takes 2–3 weeks.
Should we buy the tiles ourselves?
You can choose them yourself, or we can select them together. Materials are listed as a separate line in the estimate, so you can see what you are paying for.
Do you provide a warranty on waterproofing and tiling?
Yes, we provide a guarantee for the works; its terms are written into the contract and the handover certificate.